BUILDING UPDATE

Building Update
Progress to Date:
- Structural steel topping out
- Completion of miscellaneous perimeter support steel
- Footing backfill in progress
- Deck preparation for concrete pour Level 2
- Level 2 building information modeling coordination review pricing
- Cost event pricing
- Exterior façade elements
Two-Week Look Ahead:
- Epic deck delivery
- Completion of undercut and haul off
- Elevated slab pours
- Building Information Modeling coordination drawings submitted for Level 1
- Mobilization for start of exterior framing
- Mechanical, electrical and plumbing trades mobilize
- Start underground utility installation