[ skip to content ]

BUILDING UPDATE

Building Update

Progress to Date:

  • Structural steel topping out
  • Completion of miscellaneous perimeter support steel
  • Footing backfill in progress
  • Deck preparation for concrete pour Level 2
  • Level 2 building information modeling coordination review pricing
  • Cost event pricing
  • Exterior façade elements

Two-Week Look Ahead:

  • Epic deck delivery
  • Completion of undercut and haul off
  • Elevated slab pours
  • Building Information Modeling coordination drawings submitted for Level 1
  • Mobilization for start of exterior framing
  • Mechanical, electrical and plumbing trades mobilize
  • Start underground utility installation

Published on: March 1, 2013